The substation of this project is basically completely symmetrical. As can be seen from Figure 2, taking the firewall in the middle of the two prefabricated main equipment cabins as the boundary, on the left and right sides are respectively the prefabricated GIS cabins, prefabricated main equipment cabins, 110 kV transformers, and prefabricated capacitor cabins for Route A and Route B power supplies, and the equipment of Route A and Route B are completely independent.
The entire substation is equipped with an independent enclosure wall and operates independently from the data center park. An independent entrance out of the park is set on the south side. Only professional personnel are allowed to enter the 110 kV substation, and other personnel have no access rights, which can ensure the reliability of the substation's operation.
The GIS cabin is a single - layer prefabricated cabin. Inside, it is mainly equipped with 110 kV GIS combined electrical appliances with a rated current of 2,000 A. For each part of the design, sulfur hexafluoride (SF6) is an important arc - extinguishing medium and can be applied in GIS. Structurally, GIS is mainly divided into several parts, including voltage transformers, arresters, circuit breakers, and bushings, etc. These parts need to be correctly connected, and the reliability of each component needs to be ensured to effectively achieve the overall function [8].
The main transformer mainly uses a three - phase double - winding oil - immersed self - cooled transformer, adopting the YN grounding method, with a voltage level of [10.5 ± (2×2.5%/0.4)] kV, and the specific model is SZ11 - 80000/110.
The main equipment cabin has a two - layer structure. The first layer consists of two completely independent 10 kV output cabinet cabins, separated by a firewall, and respectively equipped with 10 kV switchgear and station service transformers corresponding to Route A and Route B power supplies. The 10 kV switchgear uses metal - clad switchgear equipped with vacuum circuit breakers. For feeder cabinets, capacitors, and station service transformers, their rated current and breaking current are 1.25 kA and 25 kA respectively; for incoming lines, they are 3.15 kA and 31.5 kA respectively. The capacity of the station service transformer is selected as 100 kVA, using a SC11 - type dry - type transformer, with a voltage of [110 ± (8×1.25%/10.5)] kV, a wiring group of Dyn11, an impedance voltage Uk = 4%, an IP40 protective enclosure, and an energy efficiency class of 2. To improve the reliability of the system, each 110 kV incoming line corresponds to two sections of 10 kV busbars, which can reduce the scope of an accident in case of a fault .
The second layer needs to be equipped with a grounding transformer, a prefabricated capacitor cabin, etc. A capacitor bank is configured in the prefabricated cabin, with differential pressure protection set, and a capacity of 6,000 kVA needs to be achieved. In addition to the above - mentioned parts, an iron - core reactor is selected in this design, with a reactance rate of 12%. A grounding small - resistance complete set device, with a grounding resistance of 10 Ω and a capacity of 400 kVA. The second layer also has a secondary room. The secondary room is specifically divided into several parts, including video surveillance, kilowatt - hour meter cabinets, electrical energy collection, fault recording, public measurement and control, telecontrol communication, relay protection, computer monitoring, intelligent auxiliary control systems, time synchronization systems, etc.
In terms of power routing, the 110 kV utility power incoming lines of Route A and Route B both enter from the 17 - m - wide short side on the right. The two routes enter in parallel, with a spacing of more than 10 m, and are respectively introduced into the prefabricated GIS cabins corresponding to Route A and Route B. The lines from GIS to transformers for Route A and Route B, the busbars from transformers to 10 kV switchgear, and the outgoing lines of 10 kV switchgear are all independent, and the spacing is more than 10 m.
The main equipment of the project, including prefabricated GIS cabins, 110 kV transformers, prefabricated main equipment cabins, etc., are all completely isolated between Route A and Route B. The power routing of Route A and Route B is completely isolated. Compared with traditional substations, it occupies less space, has a high degree of customization, is flexible and effective, and can meet the reliability requirements of data centers.
This project adopts a whole - station fully modular prefabrication method. On - site, only auxiliary facilities such as strip foundations and firewalls need to be constructed. The production and processing of modular prefabricated cabins can be carried out simultaneously with the civil engineering work, greatly reducing the amount of civil engineering work. It solves the problems of large civil engineering quantities and long construction cycles in the traditional substation construction mode, and avoids the situation where the substation construction time is restricted by civil engineering projects.
The prefabricated cabins are produced and debugged in the factory, ensuring exquisite product quality and a high - standard design implementation level, and avoiding the impact of on - site construction quality on the equipment. Structurally, the bottom frame components of the box body are connected by channel steel, and the door panels and top covers are welded with 2 - mm - thick high - quality cold - rolled plates. It has an integral structure and strong impact resistance.
The characteristics of the box body are mainly reflected in three aspects: anti - corrosion, three - layer structure, and sealing, which can meet the basic operation requirements and ensure that each component maintains a stable working state. The outer shell needs to reach a protection level of IP54 or above. The prefabricated cabins adopt a full - working - condition design and also have good wind resistance, seismic resistance, and snow load resistance to ensure the safe operation of the equipment
.
The equipment inside the cabin is highly integrated. Through the design of the cabin structure and the coordination of various internal systems, the prefabricated cabin meets the needs of equipment operation. The cabin not only takes into account the primary, secondary, and communication equipment of the 110 kV substation but also considers auxiliary systems such as environmental control, lighting, emergency lighting, fire protection, and grounding.
The cabin needs to meet high requirements, mainly involving moisture - proof and sealing properties, otherwise, the operation quality cannot be guaranteed. Considering the restrictions on length and width for road transportation in this project, the length of each transportation unit is limited to within 14 m, the width to within 3.4 m, and the height to within 4.5 m. Prefabricated cabins with larger dimensions are transported in sections, and other prefabricated cabins with relatively smaller dimensions are transported as a whole, meeting the requirements of road transportation. If the site has reached the assembly requirements, it can be transported to the site for the next - step assembly .
This project adopts a modular prefabricated method, with less civil engineering work. The main civil engineering contents include two groups of newly built main transformer foundations, four firewalls with a length of 10 m and a height of 6.5 m, two groups of GIS cabin foundations, one group of main equipment cabin foundations, one 20 - m³ accident oil pool, a 198 - m - long and 2.3 - m - high hollow enclosure wall, 14 main transformer supports, and an 80 - m - long reinforced concrete cable trench.
The prefabricated cabins adopt a mode of "factory trial assembly must be carried out to simulate the actual operation situation + split transportation to the site and then splicing and installation" on - site. All modules have been trial - assembled in the factory, and problems are discovered in a timely manner without leaving problems on - site, ensuring the on - site construction period and construction quality. On - site hoisting and assembly have a short cycle, and there is almost no raw material accumulation.
For the splicing operation of large - sized cabin parts, the on - site splicing process of "using a crane to initially position the equipment + gradually pushing with a chain block + accurately positioning with a positioning pin" is adopted. To ensure that the splicing of the cabin is "tight - fitting", the on - site hoisting photo is shown in Figure 3.
In order to meet the sealing requirements, the splicing joints are reasonably designed, mainly using the design methods of sealing materials and mechanical structures. In the box body splicing, waterproof buckles and waterproof flanges are used. After the splicing is completed, strong waterproof glue needs to be added to the joint positions, and then treated with a sealing strip. Finally, waterproof buckles and foaming materials are installed in sequence. When all processes are completed and meet high quality requirements, sealing and waterproofing can be achieved.
After each module is in place, primary and secondary connection construction is carried out. The cables inside the modules and the connection cables between them have been completely produced and installed in the factory. Only the connection cables and busbars between each module need to be installed. When each module is assembled in the factory, preliminary joint debugging and testing have been carried out, which can also shorten the on - site debugging and acceptance time.
The 110 kV substation construction project of Data Center No.1 started to communicate the plan with the Suzhou power grid and promote the preliminary procedures in early December. After going through project bidding, equipment procurement, factory production, on - site equipment foundation construction, on - site assembly, equipment debugging, and power - on acceptance, it was officially put into operation in early June. The whole process took less than 6 months, of which the time from project bid determination to project completion and power - on acceptance was about 100 days, which is the project with the shortest substation construction cycle in the data center field. Therefore, compared with traditional substations, the construction time is greatly reduced.
In addition to these advantages, due to the adoption of the modular design concept, it can be efficiently upgraded when necessary in the future, which helps to reduce the costs of maintenance and expansion, so it also shows broad development prospects.