Analysis and Countermeasures of a 145kV Disconnect Switch Maloperation Incident

Felix Spark
05/29/2025

1. Introduction
In Indonesia's power grid, 145kV high voltage disconnect switches (HVDs) are critical for maintaining transmission reliability across its archipelagic terrain. However, maloperation incidents pose significant risks to grid stability. This article investigates a 145kV HVD maloperation in an Indonesian substation, analyzing root causes and proposing countermeasures while referencing IP66 protection standards and IEC 60068-3-3 compliance to enhance operational safety.
2. Incident Overview in Indonesia
In March 2024, a 145kV disconnect switch in a Java Island substation unexpectedly opened during a routine load transfer, triggering a cascade of protective relay activations. The incident occurred in a coastal substation near Surabaya, where the switch's IP66-rated enclosure was theoretically designed to withstand tropical conditions. The unscheduled opening disrupted power supply to 120,000 households and caused a 30MW load shed, with repair costs exceeding $800,000. Post-incident analysis revealed a combination of environmental degradation and control system flaws as primary causes.
3. Root Cause Analysis
3.1 Control System Vulnerabilities
3.1.1 Parasitic Circuit Induction
The switch's DC control circuit shared a common ground with the substation's lightning protection system, a design flaw identified in 20% of Indonesian 145kV substations (2023 PLN report). During a nearby thunderstorm, transient overvoltages induced 12V DC spikes in the control wiring, mistakenly activating the switch's opening relay. Similar to a 2022 incident in Bali, where ground loops caused 145kV HVD misoperation, this case highlighted inadequate isolation between control and protection circuits.
3.1.2 Relay Aging
The switch's electromagnetic relay, rated for 100,000 operations, had exceeded 150,000 cycles without replacement. Insulation breakdown in the relay coil, detected via post-fault autopsy, allowed arcing that bridged normally open contacts. IEC 60068-3-3 thermal cycling tests later confirmed the relay's epoxy insulation degraded at >60°C, a common temperature in Indonesia's unairconditioned switchyards.
3.2 Environmental Degradation
3.2.1 IP66 Seal Failure
Despite IP66 certification, the switch's EPDM gasket showed 3mm cracks, allowing salt mist ingress. Coastal air in East Java contains 0.05mg/m³ of chloride ions, accelerating corrosion. SEM analysis of the gasket revealed ozone cracking, a result of prolonged exposure to UV radiation (annual UV index >12) and humidity >85%. This compromised the enclosure's dust/water protection, with internal components showing 0.2mm rust deposits on copper contacts.
3.2.2 Moisture-induced Insulation Degradation
High humidity (90% RH average) caused condensation on the switch's composite insulator, reducing surface resistivity from 10¹²Ω to 10⁸Ω. Partial discharge (PD) monitoring data showed PD activity increased from 5pC to 25pC over six months, a precursor to flashover. The insulator's hydrophobic coating, compliant with IEC 60068-3-3, lost effectiveness after three years in tropical conditions, failing to repel water films.
3.3 Maintenance Deficiencies
3.3.1 Inadequate Lubrication
The switch's mechanical linkage had insufficient silicone grease (NLGI Grade 2), leading to 15% increased friction in the operating mechanism. Temperature sensors recorded 40°C hotter than baseline in the pivot joints, causing stick-slip motion that generated mechanical shocks, mimicking normal opening commands. This aligns with PLN's 2024 report showing 43% of 145kV HVD maloperations relate to neglected lubrication.
3.3.2 Delayed Sensor Calibration
The switch's contact resistance sensor, calibrated to ±10μΩ, had not been verified for 18 months. Actual accuracy had drifted to ±35μΩ, masking a 120μΩ contact degradation (critical threshold: 150μΩ). Such delays in calibration are common in remote Indonesian substations, where 37% of 145kV HVDs lack scheduled maintenance due to logistical challenges.
4. Comprehensive Countermeasures
4.1 Control System Redesign
4.1.1 Isolated Grounding Architecture
Implement a star grounding system for 145kV HVD control circuits, separating them from lightning protection grounds by 5m. Install 1000V isolation transformers on control power feeds, as demonstrated in a 2023 case study in Medan that reduced transient-induced maloperations by 92%.
4.1.2 Solid-State Relay Upgrade
Replace electromagnetic relays with IEC 60950-certified solid-state relays (SSR) rated for 10⁷ operations. SSRs in a Semarang pilot project showed zero voltage spikes and 50% faster switching times, eliminating arcing risks in humid environments.
4.2 Environmental Resilience Enhancement
4.2.1 IP66 Seal System Overhaul
  • Gasket Replacement: Use fluoroelastomer (FKM) gaskets with 200°C temperature resistance, 300% elongation, and UV stabilizers, meeting IEC 60068-3-3's tropical climate annex.
  • Drainage Modification: Add 12mm weep holes with anti-insect screens to switch enclosures, reducing water pooling. A Jakarta trial showed this reduced internal humidity from 85% to 55% within 24 hours.

4.2.2 Advanced Insulation Solutions

  • Superhydrophobic Coating: Apply aerosol - based SiO₂ coatings (contact angle >150°) to insulators, extending hydrophobicity from 3 to 7 years. Field tests in Bali reduced PD activity by 80%.
  • Dehumidifier Integration: Install Peltier - effect dehumidifiers (3L/day capacity) in enclosures, maintaining <40% RH. A Sulawesi substation saw contact resistance stability improve by 65% post - installation.

4.3 Predictive Maintenance Optimization
4.3.1 IoT - Enabled Monitoring
Deploy a 4G - enabled sensor network measuring:
  • Contact resistance (0.1μΩ resolution)
  • Mechanism vibration (100Hz - 10kHz bandwidth)
  • Enclosure humidity/temperature (±1% RH, ±0.5°C)
Data is analyzed via a cloud - based AI platform (accuracy 94%) that predicts failures 72 hours in advance, as proven in a Papua pilot project that cut unplanned outages by 85%.
4.3.2 Regionalized Maintenance Schedules
Develop climate - based maintenance plans:

5. Technical and Economic Impact
5.1 Reliability Metrics Improvement

  • MTBF Increase: From 12,000 hours to 45,000 hours post - intervention, exceeding IEC 62271 - 102's target.
  • Fault Detection Time: Reduced from 4 hours to 15 minutes via real - time IoT monitoring.

5.2 Cost - Benefit Analysis

  • Initial Investment: $500,000 for a 10 - switch substation in Indonesia
  • 5 - Year Savings: $2.3 million from:
    • 75% reduction in maintenance labor
    • 90% decrease in equipment replacement costs
    • 88% minimization of downtime losses
6. Conclusion
The 145kV disconnect switch maloperation in Indonesia underscores the need for integrated solutions addressing control system vulnerabilities, environmental degradation, and maintenance gaps. By implementing IP66 - enhanced enclosures, IEC 60068 - 3 - 3 - compliant components, and IoT - driven predictive maintenance, Indonesia's 145kV grid can achieve reliability metrics on par with global standards. This approach not only mitigates maloperation risks but also supports the country's goal of a resilient, smart power infrastructure capable of meeting rising energy demands in tropical environments.
Felix Spark

Hey there! I'm an electrical engineer specializing in Failure and Maintenance. I've dedicated my career to ensuring the seamless operation of electrical systems. I excel at diagnosing complex electrical failures, from malfunctioning industrial motors to glitchy power distribution networks. Using state - of - the - art diagnostic tools and my in - depth knowledge, I pinpoint issues quickly. On this platform, I'm eager to share my insights, exchange ideas, and collaborate with fellow experts. Let's work together to enhance the reliability of electrical setups.

Inquiry
Download
Experts Electrical is dedicated to serving the personnel in the global power industry.
Join Experts Electrical, not only can you discover power equipment and power knowledge, but also canhnd like - minded friends!